602 418-7118 Fields of Special Competence ·Construction management, plant
operation/maintenance, QA/QC Management and inspection with over 34 yrs
experience. § Troubleshooting,
repair, maintenance, design and operation electrical and electronic control
systems, SCADA systems, associated panel design, instrumentation and
electrical. Interpreted maintenance and repair information, procedures,
system drawings, repair, maintenance and operation of pumps, valves, variable
frequency drives, instrumentation, radios, power monitoring equipment,
back-up power generators, programmable logic controllers (PLCs), chlorine
systems, ultra violet disinfections systems switch gear-motor control centers
and all equipment associated with water/ wastewater plants and pump stations.
Understand NFPA 70 E for compliance with arc flash. § Proficient
in inspections and document control for construction to include civil
(concrete & earth work), mechanical and electrical disciplines. § Proficient
in MS Word, MS Excel, Outlook, Windows, Modicon and Allen Bradley PLC’s. § Develop
short and long range work plans, including resource requirements, budget
estimates and various required reports. Employment Highlights RES
Americas July 2014- Dec 2015 Quality
Manager ·Border Winds Wind Farm Project
Rolla, ND – Quality Manager, responsible for all aspects of electrical,
civil, mechanical, structural installation per specifications and plans for
turbine construction of a Vestas150MW wind farm. Wrote site inspection test
plans, ensured all appropriate testing was conducted per site QA/QC plan and
all test forms were complete for turnover packages to the client associated
with all disciplines. Submitted required Non Conformance Reports, Deviation
Reports, Deficiency Reports and other reports required by the site QA/ QC
site quality program. Jacobs
Engineering April 2006-April 2014 QA/QC
Lead Electrical Inspector ·Freeport McMoran Copper Mine Morenci
– QA/QC inspections for 0ver 1.5 billion dollar expansion. Inspected all
aspects for electrical installation, including duct banks, conduit runs,
cable trays, wire pulling, equipment installation, panel installation, system
testing and system start-up, also inspected other disciplines to include
Civil, Mechanical, Structural and other site needs per Specifications and
plans. Wrote site inspection test plans, witnessed all appropriate testing
per site QA/QC plan and ensured all test forms were complete for turnover
packages to the client. Submitted required Non Conformance Reports, Deviation
Reports, Deficiency Reports and other reports required by the site QA/ QC
site quality program. Site
Lead ·Shell Albian Oil Sands - Review
P&ID’s, Site Plan Drawings and General Arrangement Drawings to collected
information to do site walk-downs to verify equipment tag data at an oil
sands processing plant for use in the SAP program for maintenance tracking.
In charge of coordinating daily crew safety briefs and safe work procedures
associated with the mining operations at Jack Pine Mine. ·Kennecott Utah Copper Corporation –
Reviewed Instrument Data Sheets and compared to the P&ID’s and for
technical accuracy. Conducted bid analysis for data from
manufactures/suppliers to ensure compliance with bid specifications. Client
Rep. ·Nogales International Wastewater
Treatment Plant - Worked as construction inspector/owner represenitive
during construction phase of the construction of a 17MGD wastewater plant,
monitoring contractors for correct installation per specifications and
contract documents. Coordinated with contractors and local utility groups to
inspect the installation of underground utilities and piping, inspected
backfills, concrete quality and all civil, mechanical and electrical aspect
of the project. Monitored job site for safety and work practices in
compliance with OSHA standards and other local standards. ·City of Phoenix - Instrumentation
and Control Services, City of Phoenix: Technical Support. The
purpose of the project is to enforce the City’s Process Control System
Standards to assure flawless installation of instrumentation and control
equipment during construction at the plant. Under the project, construction
installation inspections, commissioning testing, and calibrations of I&C
systems, I&C Standards Development, provide support to design consultants
and construction contractors to ensure that they are complying with the
City’s Process Control Standards, review shop drawings for content and
compliance with City standards, performing commissioning, troubleshooting,
redlining and developing record drawings. EMA
Inc. Phoenix, Arizona / San Diego California, March 2000-March 2006 Construction
Manager/Senior Control Systems Engineer Senior
Control System Engineer designing SCADA systems for large water systems,
assisted in writing and reviewing system construction specifications,
specifying parts to be used, and estimate job costs. ·Worked as construction manager
during construction phase of the job monitoring contractors for correct
installation per the specifications. Coordinated with other contractors and
local utility groups to inspect the installation of underground utilities.
Inspected backfills, concrete and asphalt paving, ensuring the work conformed
to client or city standards. Monitored job site for safety and work practices
in compliance with OSHA standards. Involvement in permit issuances and right
of way planning. Conducted monthly progress meetings with San Diego city
staff to convey construction project progress for CIP project and potential
opportunities in cost savings. Conducted progress meetings with contractors
to ensure any construction issues were address immediately and to stay
informed of potential scheduling or time issues that could result in delays.
Maintained logs and schedules for the project. ·Designed SCADA control system for 60
pump stations, 140 remote pressure and flow locations; to include site
surveys and site layout and construction installation drawings and
construction cost estimates. Scope of the work was to upgrade remote control
panels and electrical system for site monitoring and pump control. Updated
site drawings in AutoCad to reflect design changes. Started and commissioned
all sites. ·Designed Remote control panels,
estimated construction costs. Randomly monitored panel construction for
quality at the contractor’s facility. Conducted factory acceptance test. TAVA TECHNOLOGIES, Phoenix, Arizona, March
1998-March 2000
Service Manager
Managed
a control systems group; responsible for bidding, designing, building, and
installing integrated systems for clients to automate and update systems to
operate automatically in Industrial and manufacturing facilities and
Water/wastewater,, SCADA, and other associated systems. § Troubleshoot
and repair electronic, electric, and other automatic digital and analog
controlled instruments and high-voltage electric equipment. § Install,
maintain, and repair remote telemetry systems including programmable logic
controllers, modems, and associated wirings. § Calibrate
process control instrumentation and perform scheduled maintenance. § Operate
and maintain personnel computers and write software program changes used for
system monitoring and report generation. § Review
and evaluate electronic, electric, and computer specifications for facility
construction projects. § Review
and submit budgets for annual divisional operations. CITY OF CHANDLER, Arizona, April 1991-Febuary
1998
Instrumentation
Engineer
Responsible
for the installation, maintenance, and repair of electric, electronic and
other automatic digital and analog controlled equipment used in water
production, treatment, distribution, and waste water pumping, collection, and
treatment facilities. Duties entail troubleshooting and diagnosing integrated
circuits, printed circuit boards as well as chemical and telemeter equipment. § Calibrate
all process control instrumentation and perform scheduled maintenance at
remote pump sites and water treatment plants. § Install,
maintain, and repair remote telemetry systems including microprocessor based
control units, modems, and associated wirings. § Troubleshoot
and repair electronics, electric and other automatic digital and analog
controlled instruments and high voltage electric equipment. § Diagnosed
and troubleshoot single-mode and multi-mode fiber optic networks. § Designed
and managed a construction project and contractors to upgrade a remote telemetry
system, (30) reservoir pump sites to a PLC based RCP SCADA system. SCOTT
CONTAINER PRODUCTS, Phoenix, Arizona, March 1989-March 1991
Responsible
for Building, installing and testing electronic controls for automated
production equipment. ■
Wired, tested,
troubleshot, and repaired electronic components in manufacturing. ■
Assembled and wired
container production equipment. ■
Redesigned inspection
equipment electrical circuits, significantly
improving automated container packing functions
and product
accountability.
UNITED
STATES NAVY, July 1979-March 1989
Interior
Communication Electrician (E-6) As
work center supervisor managed Interior Communication staff in maintenance
and repair of complexes electrical systems used in the control of an U.S.
Ballistic Missile Submarine. ▪
Interface with shipyard
and contractor representatives, coordinating activities, and providing
technical support during troubleshooting and repair of electronic circuits
and equipment during new construction of a new trident submarine. ▪
Repaired analog and
digital circuits associated with control functions of hydraulic and pneumatic
operated valves utilized in vital ship control functions. ▪
Operated and repaired
vital equipment required operating a submarine. ▪
Responsible for writing
and administering lesson plans for training divisional personnel on various
vital atmosphere monitoring and ship control systems. |
|
|
|||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
|
|